330:148(g). Machine Design
Home work
S. No. |
Project title |
Weightage, % |
Date of submission |
1 |
Design process | 4 | August 27, 2007 |
2 |
Stress and strain | 4 | September 10, 2007 |
3 |
Combined stresses | 4 | September 17, 2007 |
4 |
Fasteners and Power screws | 4 | September 24, 2007 |
5 |
Spring design | 4 | October 8, 2007 |
6 |
Spur gear design | 4 | October 15, 2007 |
7 |
Other Gear design | 4 | October 22, 2007 |
8 |
Belts and chains | 4 | October 29, 2007 |
9 | Shafts | 4 | November 5, 2007 |
10 | Clutch, Brake and Bearings | 4 | November 26, 2007 |
Class work
S. No. |
Project title |
Weightage, % |
Date of submission |
1 |
Force, work and Power | 1 | August 20, 2007 |
2 |
Stress and strain | 1 | August 27, 2007 |
3 |
Combined stresses | 1 | September 10, 2007 |
4 |
Fasteners and Power screws | 1 | October 8, 2007 |
5 |
Gear design | 1 | October 22, 2007 |
6 |
Belt design | 1 | October 29, 2007 |
7 |
Keys and couplings | 1 | November 5, 2007 |
8 |
Clutches and brakes | 1 | November 12, 2007 |
9 | Shafts | 1 | November 26, 2007 |
10 | Bearings | 1 | December 3, 2007 |
Useful material
Sample report | |
Mail to P N Rao
Last Modified: