Renaissance Partnership for Improving Teacher Quality Work Plan for Year 4 (2002-2003)

1. Accountability Systems

Project Goal: To become accountable for the impact of the teacher candidates and graduates on student learning. Improve teacher performance in key areas and show increase in teachers’ ability to facilitate learning of all students.

Five Year Objective: All eleven Renaissance institutions will develop and implement program and course changes that support teacher work samples, mentoring, and the ability of teacher candidates to facilitate learning of all children.

Year 4 Objectives: 

  • All eleven institutions will bring their accountability systems to full operation.
  • All eleven institutions will collect and report performance data on teacher candidates linked to P-12 student learning
  • All eleven institutions will collect and report data on performance of graduates

Activity

Benchmarks

Time Line

Responsible Party

Resources Needed

  1. Disseminate working models of performance accountability systems
Models from three institutions distributed and on the project web site November 2002 Project Director, Assessment Coordinators Released time for Assessment Coordinators
  1. Provide technical assistance events and options to member institutions
Description and report of technical assistance events January 2003 June 2003 Project Director, Assessment Coordinators Released time for Assessment Coordinators of institutions with working models
  1. Develop and adopt a common format for collecting performance data on teacher candidates
Approved common format on web site February 2003 Project Director, Tony Norman Travel for Assessment Coordinators to St. Louis work sessions in January and June of 2003
  1. Develop and adopt a range of options for collecting and reporting data on teacher graduates
Concept paper on range of options March 2003 Tony Norman and Peter Denner Released time for Assessment Coordinators
  1. Institutions develop Year 4 work plans for system development, candidate data collection and teacher graduate data collection
Institution work plan document January 2003 Assessment Coordinators Released time for Assessment Coordinators
  1. Institutions implement Year 4 plans
Report of implementation progress June 2003 Assessment Coordinators Released time for Assessment Coordinators
  1. Institutions report progress on performance accountability system
Report of implementation progress August 2003 Assessment Coordinators Released time for Assessment Coordinators
  1. Institutions report performance data on teacher candidates and graduates
Data report August 2003 Assessment Coordinators Released time for Assessment Coordinators
  1. Institution data is aggregated and reported for the project
Project report September 2003 Project Director and Tony Norman Released time for Assessment Coordinators travel to St. Louis work session in January and June of 2003


Outcome:  

  • Fully operational data management systems that collect and report candidate performance data at admissions, pre-student teaching, exit from program and first year teacher graduates. 

Measure:  

  • Institution descriptions of performance accountability data management systems
  • Institution reports on performance of teacher candidates relative to teacher work samples
  • Institution reports on performance of first year teacher graduates

TOP

2.  Teacher Work Samples

Project Goal: To become accountable for the impact of the teacher candidates and graduates on student learning. Improve teacher performance in key areas and show increase in teachers’ ability to facilitate learning of all students.

Five Year Objective: All eleven Renaissance institutions will develop and implement the use of teacher work samples in their teacher education programs as a means of improving teaching skills and increasing the teacher’s impact on student learning.

Year 4 Objectives: 

  • Institutions will expand the implementation of teacher work samples toward the inclusion of all teacher candidates
  • Institutions will increase the performance levels of student teachers on teacher work samples

Activity

Benchmarks

Time Line

Responsible Party

Resources Needed

  1. Implement TWS fall program with expanded resources
Fall progress report January 2003 TWS Coordinator Released time of TWS Coordinator 
  1. Institutions establish a process to develop site validity and reliability data
Plan document January 2003 Assessment Coordinators Released time of TWS Coordinator and Assessment Coordinator for travel to St. Louis for January and June 2003 work sessions
  1. Convene work groups to develop “Assessment Tools for Teachers” manual
Next draft of assessment tools manual  January 2003 Project Director and Tony Norman Travel for assessment tools task force work group (one session in fall 2002, one session in spring 2003) support for manual development
  1. Conduct January 2003 work session to report fall semester performance and progress, review assessment materials, benchmark new TWS exemplars and share successes and challenges
Agenda and report of progress at work session February 2003 Project Director Travel for institution work groups, including TWS Coordinator, Assessment Coordinator and Mentoring Coordinator to St. Louis work sessions in January and June 2003
  1. Implement TWS spring program with expanded resources
Spring progress report June 2003 TWS Coordinator Released time for TWS Coordinator for support for TWS training
  1. Convene work group to make final revisions on “Assessment Tools for Teachers” manual
Final draft of assessment tools manual August 2003 Project Director and Tony Norman Travel for assessment tools task force work group (one fall 2002 and one spring 2003 work sessions) support for manual development 
  1. Plan and conduct June 2003 work sessions to report spring semester performance progress, present and share instructional materials, benchmark new exemplars and establish scoring agreement across institutions
Agenda and report of progress at work session  July 2003 Project Director Travel for institution work groups, including TWS Coordinator, Assessment Coordinator and Mentoring Coordinator to St. Louis work sessions in January and June 2003


Outcome:  

  • A minimum of 1,000 teacher work samples will be completed across the eleven project sites
  • Each institution will close the gap towards 100% proficiency (level 3) by 25% 

Measure:  

  • Report the number of completed and scored work samples by institution
  • Report on scored level of performance by institution

TOP

3.  Mentoring Teams

Project Goal: To become accountable for the impact of the teacher candidates and graduates on student learning. Improve teacher performance in key areas and show increase in teachers’ ability to facilitate learning of all students.

Five Year Objective: All eleven Renaissance institutions will develop and implement a team mentoring model consisting of school practitioners, arts and science faculty and teacher educators that facilitate the ability of teachers to impact student learning in partner schools.

Year 4 Objectives: All project sites will establish a mentoring model (framework, organization, process and implementation plan) that:

  • Involves teacher educators, arts & science faculty and school practitioners
  • Is functional for the context, conditions and resources at each respective site
  • Facilitates the performance of candidates on teacher work samples to achieve proficiency or above

Activity

Benchmarks

Time Line

Responsible Party

Resources Needed

  1. Institutions implement fall mentoring training
Fall progress report January 2003 Mentoring Coordination Released time of Mentoring Coordinator support for mentoring training; released time for mentors – arts & sciences and school practitioners 
  1. Institutions review existing mentoring structures and processes and revises existing model to improve candidate performance
Inventory response report January 2003 Mentoring Coordinator Released time of Mentoring Coordinator
  1. Mentoring manual work group develops working draft
Mentoring manual draft January 2003 Project Director, Georgea Langer and Jean Behrend Travel for mentoring manual task force to work session in fall 2002 to support manual development
  1. Project sites develop plans to remove key barriers identified in spring 2002 and implement “revised mentoring model”
Institution plans documents January 2003 Mentoring Coordinator Released time of Mentoring Coordinator
  1. Institutions implement spring mentoring training
Spring progress report June 2003 Mentoring Coordinator Released time of Mentoring Coordinator to support mentoring training; released time for mentors – arts & sciences and school practitioners
  1. Project sites implement draft of mentoring manual in spring semester 2003 to provide feedback
Feedback report June 2003 Mentoring Coordinator Released time of Mentoring Coordinator 
  1. All sites evaluate their mentoring processes and results for fall 2002 and spring 2003 and complete a revised mentoring model for implementation in Year 5 of the project
Revised model September 2003 Mentoring Coordinator Released time of Mentoring Coordinator
  1. Mentoring work group produces revised draft of mentoring manual
Final draft published  August 2003 Project Director, Georgea Langer and Jean Behrend Travel for mentoring manual task force to work session in spring 2003


Outcome:  

  • All sites will develop and implement a team mentoring model and process for the purpose of facilitating high levels of performance on teacher work samples.

Measure:  

  • Individual site reports on their mentoring model: components, organization, processes, implementation and results

TOP

2b. & 3b.  Systemic Program Revision and Improvement in Quality of Graduates

Project Goal: To become accountable for the impact of the teacher candidates and graduates on student learning. Improve teacher performance in key areas and show increase in teachers’ ability to facilitate learning of all students.

Five Year Objective: All eleven Renaissance institutions will fully implement an accountability system that regularly collects and reports data on the impact of their graduates on student learning.

Year 4 Objectives: 

  • All project institutions complete revisions on the more than 80 content, measurement and pedagogy courses identified in the spring of 2002 to address the seven TWS processes
  • Institutions develop a structure and process to review candidate and graduate performance data on at least an annual schedule and make appropriate improvements

Activity

Benchmarks

Time Line

Responsible Party

Resources Needed

  1. Inventory of courses under revision and development of a plan to monitor development
Inventory submitted January 2003 Institution Coordinator Released time for Institutional Coordinator
  1. Design of an institutional systemic plan (structure and process)
Systemic plan document January 2003 Institution Coordinator Released time for Institutional Coordinator
  1. Share draft plans across institutions; discuss insights and challenges
Plan exchange on project web site with responses January 2003 Project Director Released time for Institutional Coordinator
  1. Complete systemic course and program revisions plans and processes
Report of revision progress June 2003 Institution Coordinator Released time for Institutional Coordinator
  1. Implement plan and report on the results
Report of revision progress June 2003 Institution Coordinator Released time for Institutional Coordinator
  1. Report on completion of course revisions in Year 4
Combined project report for revisions across all 11 institutions September 2003 Project Director Released time for Institutional Coordinator


Outcomes:  

  • Completed revisions of course descriptions and syllabi
  • An approved systemic course and program revision plan

Measure:  

  • Documented course changes
  • Plan document; description of process

TOP

4. Education Partnerships with Business

Project Goal: To become accountable for the impact of the teacher candidates and graduates on student learning. Improve teacher performance in key areas and show increase in teachers’ ability to facilitate learning of all students.

Five Year Objective: All eleven Renaissance institutions will establish dynamic partnerships with businesses that provide increased learning opportunities for teacher candidates and/or students in partner schools.

Year 4 Objective: The eleven Renaissance institutions will define as a group and individually what role they want business to serve in improving teacher quality.

Activity

Benchmarks

Time Line

Responsible Party

Resources Needed

  1. Appoint a business partnership task force
Task force named December 2002  Project Director Coordination time of Project Director
  1. Conduct work session to develop concept paper draft
Concept paper produced January 2003 Project Director Coordination time of Project Director
  1. Project-wide review of draft
Plan circulated on project web site April 2003 Project Director Coordination time of Project Director
  1. Task force revises draft and develops plan for Year 5
Draft revised and plan developed June 2003 Project Director Coordination time of Project Director
  1. Project-wide review of Year 5 plan
Report of review August 2003 Project Director Coordination time of Project Director
  1. Production of approved concept paper and plan
Plan part of Year 5 project work plan September 2003 Project Director Coordination time of Project Director


Outcome:  

  • A concept paper describing the role Renaissance partnership institutions want business and industry to serve in teacher and school leader preparation, building the capacity of school practitioners and supporting initiatives to improve teacher quality
  • A project plan to engage business and industry consistent with roles and purposes communicated in the concept paper

Measure:  

  • Individual institution statements signed by institution provosts

TOP

5.  Networking

Project Goal: To become accountable for the impact of the teacher candidates and graduates on student learning. Improve teacher performance in key areas and show increase in teachers’ ability to facilitate learning of all students.

Five Year Objective: All eleven Renaissance institutions will collaborate to develop an electronic network that (1) supports sharing of information, ideas, training materials, instructional resources, and research results, and (2) stimulates interaction and dialogue among teacher educators, arts and science faculty, and school practitioners about improving teaching and learning.

Year 4 Objectives: Transform the project web site from a compendium of information to a dynamic tool for promoting research-based ideas, providing materials for instruction, improving candidate performance, inter-site and intra-site communication and sharing of research results.

Activity

Benchmarks

Time Line

Responsible Party

Resources Needed

  1. Evaluate existing web site contents, format development, structure and use by role groups
Evaluation summary report December 2002 Project Director and Web Mistress Coordination and leadership time for Project Director; coordination time of Institution Coordinator; released time of web mistress and web site staff at University of Northern Iowa
  1. Develop operational goals of web site for September 2004 (end of Title II Project)
Long term goal document January 2003 Project Director and Web Mistress Coordination and leadership time for Project Director; coordination time of Institution Coordinator; released time of web mistress and web site staff at University of Northern Iowa
  1. Develop improvement, restructuring plan to close the gap between existing operations and future goals
Restructuring plan circulated April 2003 Project Director Coordination and leadership time for Project Director; coordination time of Institution Coordinator; released time of web mistress and web site staff at University of Northern Iowa
  1. Maintain and develop existing successful web site components
  • project component descriptions
  • project site news
  • project events, work sessions and training opportunities
  • training materials
  • TWS benchmarked exemplars
  • concept papers and materials
  • PowerPoint presentations
Expanded web site October 2002 to September 2003 Project Director and Web Mistress Coordination and leadership time for Project Director; coordination time of Institution Coordinator; released time of web mistress and web site staff at University of Northern Iowa
  1. Pilot new features and improved features based on plan
New features on web site January 2003 to September 2003 Project Director and Web Mistress Coordination and leadership time for Project Director; coordination time of Institution Coordinator; released time of web mistress and web site staff at University of Northern Iowa


Outcome:  

  • Improved web site format, structure, delivery and promotion strategies

Measure:  

  • Level of response by different user groups

TOP

6.  Research Program

Project Goal: To become accountable for the impact of the teacher candidates and graduates on student learning. Improve teacher performance in key areas and show increase in teachers’ ability to facilitate learning of all students.

Five Year Objective: 5 year objective needs to be replaced with: All eleven Renaissance institution will collaborate to develop a research program that links teacher candidate performance with K-12 student learning.

Year 4 Objectives: 

  • Publish reports on:
    • change in teacher candidate performance
    • change in faculty practices and behaviors resulting from use of teacher work samples
    • program changes resulting from development and implementation of teacher work sample
    • acceptable evidence of P-12 student learning
    • credibility studies (validate and reliability) of the Renaissance model for teacher work samples
  • Pilot studies at five institutions which measure growth of P-12 students taught by graduates who completed teacher work samples
  • Plan and prepare for all sites to collect P-12 achievement data on students taught by teacher graduates

Activity

Benchmarks

Time Line

Responsible Party

Resources Needed

  1. Complete and publish six research studies in progress
Draft of completed reports June 2003 Respective Assessment Coordinators Released time for Assessment Coordinators
  1. Design a pilot study for achievement of students taught by graduates in five institutions
Draft study January 2003 Tony Norman and Peter Denner Released time for Assessment Coordinators in five institutions
  1. Pre-test for P-12 students at five sites
P-12 students tested January 2003 Project Director and Assessment Coordinators at respective sites Released time for Assessment Coordinators in five institutions for P-12 assessment materials
  1. Post test and analysis of achievement gains for students of graduates at five sites
P-12 students post tested with results posted July 2003 Project Director and Assessment Coordinators at respective sites Released time for Assessment Coordinators in five institutions for support for scoring P-12 assessments
  1. Design P-12 achievement study for project year 5
Design approved by Assessment Coordinators June 2003 Tony Norman and Assessment Coordinators Released time for Assessment Coordinators
  1. Prepare and obtain resources for studies of P-12 student achievement in Year 5
Proposal funded June 2003 Project Director Released time for Assessment Coordinators for pre-post assessments for P-12 ($7 per P-12 student)


Outcomes:  

  • Five published research reports
  • Results of pilot study of P-12 students taught by graduates who completed teacher work samples
  • Design and plan for Year 5 study of P-12 student growth for graduates at all 11 institutions

Measure:  

  • Quality of reports and research design